Home » Case studies » BAB Integrated Facilities Project
BAB Integrated Facilities Project
Helical Turbine Meters for Water Injection Meters
| Ref | BAB Integrated Facilities Project |
|---|---|
| Location | United Arab Emirates |
| Year | 2019 |
| Application | Helical Turbine Meters for Water Injection |
| Contractor | CPECC |
| End user | ADNOC |
Products & services
Metering & Technology SAS (M&T) has successfully delivered 114 Liquid
Helical Turbine Flow Meters to CPECC for the BAB Integrated Facilities Project
(BIFP) of ADNOC Onshore.
The project’s scope of work involves the expansion of integrated processing
facilities at the Thamama-A, Thamama-B, and Thamama-H production zones
located at Habshan, Abu Dhabi. The project will have a total sustainable oil
production rate of 450,000 barrels a day.
The 1’’ and 2’’ turbine ow meters delivered by M&T have been manufactured
by it’s parent company Oil & Gas Measurement Ltd (OGM) in the UK.